Description: Onsite Engineering was challenged by the Massachusetts Department of Environmental Protection (MassDEP) to design a system in compliance with current wastewater regulations by upgrading the previous septic systems to a decentralized on-site water resource recovery facility (WRRF) to provide the RV resort with a more enjoyable and immersive experience for its visitors.
Wastewater System – Sharon, Massachusetts
Project: Solution for Technically Challenging TOC Limit
Client: CHA Engineers
Location: Sharon, MA
Scope of Work: Amphidrome® and EnBac™ Process
Description: CHA Engineers was required by the Massachusetts DEP to design a 39,000 gpd treatment system with stringent TOC limits because it discharges treated wastewater into a drinking water Wellhead Protection Area.
Description: Stantec Engineers was challenged by the Massachusetts Cape Cod Commission to design a nitrogen-reducing system with stringent limits for Epoch Assisted Living in Mashpee, MA.